Category: City News

Far Hills Storm Sewer Reconstruction Project Update – 11/30

Schedule Change for Upcoming Work: It was last reported that the curb on the north side of Dellwood would occur this week, week of 11/27. Due to sustained freezing temperatures, the subcontractor (Oglesby) is now tentatively scheduled to replace the curb early in the week during the week of 12/3. Kinnison Excavating will begin demolition … Continued

Far Hills Storm Sewer Reconstruction Project Update – 11/17

Project Highlights: Kinnison Excavating and subcontractors have substantially completed restoring the areas within Phase 1 of the Far Hills Storm Sewer Replacement project, which covers northbound Far Hills Ave., Dellwood Ave. and extends across E. Schantz Ave. Dellwood Avenue Concrete Roadway Restoration:  Kinnison is finished with all roadway restoration along Dellwood, save some minor patches … Continued

Far Hills Storm Sewer Reconstruction Project Update – 11/3

Project Highlights: Kinnison Excavating and subcontractors have made progress in restoring the areas within Phase 1 of the Far Hills Storm Sewer Replacement project, which covers northbound Far Hills Ave., Dellwood Ave. and extends across E. Schantz Ave. Liapis Landscaping resodded ~2,000 square feet within an easement between a couple of lots on Dellwood affected … Continued

Far Hills Storm Sewer Reconstruction Project Update – 10/24

The top priority is roadway, curb and associated site restoration along Dellwood between Far Hills and E. Schantz, and along the east side of Far Hills heading south from Dellwood.  City staff has applied heavy pressure on the contractor (and concrete sub-contractor) to complete this work as soon as possible.  The restoration schedule is as … Continued

Far Hills Storm Sewer Reconstruction Project Update – 10/6

Project Highlights: Kinnison Excavating has made significant progress in Phase 1 of the Far Hills Storm Sewer Replacement project, which covers Dellwood Ave. and extends across E. Schantz Ave. Despite some delays due to gas and water main conflicts and inclement weather, the storm sewer installation is now nearly complete in this phase. The team … Continued

Fall Leaf Collection begins October 9

We will begin our annual leaf collection program on Monday, October 9.  As in previous years, the program will provide bi-weekly leaf pickups of all areas throughout the city.  The city is divided into ten sections with each being collected on a 2-week interval as shown on the map below.    The program is scheduled … Continued

Far Hills Storm Sewer Reconstruction Project Update – 9/15

We are pleased to provide you with the latest developments from the ongoing Far Hills Storm Sewer Replacement project. The hardworking team at Kinnison Excavating has been diligently progressing, and here are the highlights from the past couple weeks: Project Highlights: In the past couple of weeks, Kinnison Excavating focused its efforts on the following … Continued

Garden Road Concrete Street Repair Project

Construction will begin Friday, September 8 on Garden Road between Patterson Road and Lookout Drive. The project includes concrete street panel removal and replacement. Work is anticipated to continue through mid-October. Please contact Chris Kuzma, PE at 937-298-0777 with questions about the project. Garden Road Resident Notification Letter

Lost & Unclaimed Property

Over the past two years, the Public Safety Department has recovered pieces of property, some of which include bicycles and scooters.  An inventory of these items is kept and when quantities get too great to be maintained, the items are released from the Safety Department’s possession.  Most of this property is donated.  For example, all … Continued

Close window