Kinnison Excavating has begun mobilizing to Oakwood for the Far Hills Storm Sewer project. A tentative schedule for the next couple of weeks is as follows:

  • Wednesday, July 19 – Friday, July 21:  Kinnison mobilizes to Oakwood. Prep work such as utility marking, tree marking, construction staking/surveying, staging materials, and equipment.
  • Wednesday, July 19 – Begin “no parking” on Dellwood.
  • Thursday, July 20:  Begin tree removal and clearing & grubbing.
  • Friday, July 21 – Tuesday, July 24:  Begin demolition of home at 1313 Far Hills. Begin closure of outside lanes of northbound and southbound Far Hills Avenue.
  • Monday, July 23:  Kinnison Excavating to begin excavation along northbound Far Hills Avenue, Dellwood Avenue, and OHS/OJHS parking lot. This phase of the project is projected to be completed in 4-5 weeks.