Far Hills Storm Sewer Reconstruction Project Update – 5/3

Posted on May 3, 2024


Project Highlights:

Storm Sewer Construction on Forrer Boulevard (Phase 3): Kinnison Excavating crews have completed the majority of storm sewer construction along Forrer Boulevard, from Far Hills to E. Schantz. We anticipate that construction of the sewer main will be completed by the week of May 13, weather permitting.

Upcoming Work:

 Reconstruction of Devereux Drive: Kinnison will be placing the final two curb inlet structures along Devereux Drive then reconstructing and resurfacing the roadway within the project limits once Phase 3 is complete. This work is anticipated to begin as early as May 20. This is the final phase of the project.