Two legal notices about sidewalk assessments were printed in the May 15 edition of the Oakwood Register and have caused some confusion. These were routine notices related to the city’s annual Sidewalk, Curb, and Driveway Apron Repair Program.  The notices list all streets that are within the geographic limits of the 2022 and 2023 project areas, including streets that may not have sidewalks.  Residents should note that this does not mean new sidewalks are, or were, to be constructed.  These notices pertain to repairs only, and to work that was done in 2022 and 2023.  The only costs being assessed are costs that remain unpaid after the affected property owners were invoiced.

Far Hills Storm Sewer Reconstruction Project Update – 5/3

Posted on May 3, 2024


Project Highlights:

Storm Sewer Construction on Forrer Boulevard (Phase 3): Kinnison Excavating crews have completed the majority of storm sewer construction along Forrer Boulevard, from Far Hills to E. Schantz. We anticipate that construction of the sewer main will be completed by the week of May 13, weather permitting.

Upcoming Work:

 Reconstruction of Devereux Drive: Kinnison will be placing the final two curb inlet structures along Devereux Drive then reconstructing and resurfacing the roadway within the project limits once Phase 3 is complete. This work is anticipated to begin as early as May 20. This is the final phase of the project.

Close window