Far Hills Storm Sewer Reconstruction Project Update – 6/27

Posted on June 27, 2024


Project Highlights:
1313 Far Hills Avenue (Vacant Lot): The lot at 1313 Far Hills has been advertised for sale. Details may be found at the following link: 1313 Far Hills for Sale

Upcoming Work:
Devereux Drive Concrete Roadway: Crews will be on site tomorrow morning, Friday, June 28, to begin pouring the concrete roadway. Pouring the concrete roadway is anticipated to take 2-3 days. Each section requires 5-7 days to cure before opening the roadway to local traffic.

Contact Information Reminder:
If you have any questions or concerns during this project, please reach out to Chris Kuzma, City Engineer, at (937) 298-0777 or via email at fhss@oakwoodohio.gov. Your questions, concerns, and comments are always welcome.