Far Hills Storm Sewer Reconstruction Project Update – 9/15

We are pleased to provide you with the latest developments from the ongoing Far Hills Storm Sewer Replacement project. The hardworking team at Kinnison Excavating has been diligently progressing, and here are the highlights from the past couple weeks: Project Highlights: In the past couple of weeks, Kinnison Excavating focused its efforts on the following … Continued

Far Hills Storm Sewer Reconstruction Project Update – 8/18

UPDATE: Friday, August 18, 2023 Kinnison Excavating has been hard at work, and continues to make great progress. We’re pleased to share the highlights from the past week (week of August 14th): Project Highlights: Kinnison Excavating focused their efforts on the storm sewer replacement along the curb lane of northbound Far Hills, between Greenmount Boulevard … Continued

Far Hills Storm Sewer Reconstruction Project Update – 8/11

Kinnison Excavating finished demolishing the existing home at 1313 Far Hills the week of July 31. They then began with performing small excavations along Far Hills Avenue, Dellwood Avenue, and in the parking lot on the south side of OHS/OJHS to verify locations of utilities that the new storm sewer pipe will be crossing. Kinnison … Continued

Far Hills Storm Sewer Reconstruction Project Update

Kinnison Excavating has scheduled the demolition of the primary structure at 1313 Far Hills Avenue for Friday, July 28. The south parking lot at OHS/OJHS will be closed from 7/31 through 8/9. Crews will begin clearing brush and trees between the parking lot on 7/31 and will begin excavation on 8/1. The 100-Block of Dellwood … Continued

Far Hills Storm Sewer Reconstruction Project – Tentative Schedule

Kinnison Excavating has begun mobilizing to Oakwood for the Far Hills Storm Sewer project. A tentative schedule for the next couple of weeks is as follows: Wednesday, July 19 – Friday, July 21:  Kinnison mobilizes to Oakwood. Prep work such as utility marking, tree marking, construction staking/surveying, staging materials, and equipment. Wednesday, July 19 – … Continued

Far Hills Storm Sewer Reconstruction Project – Kinnison Excavating

The project was successfully bid and is awarded to Kinnison Excavating. We anticipate that Kinnison will begin moving project materials and equipment into Oakwood in late June with construction beginning in July. Work will continue through the summer and fall months.

Far Hills Storm Sewer Reconstruction Project

From the June/July Oakwood Scene newsletter: A large storm sewer replacement project will be completed on Far Hills Avenue at Greenmount Boulevard; on Dellwood Avenue from Far Hills Avenue to E. Schantz Avenue; Forrer Boulevard from Far Hills Avenue to E. Schantz Avenue; and along a section of Devereux Drive north of Forrer Road. Construction … Continued