Far Hills Storm Sewer Reconstruction Project Update – 6/27

Project Highlights: 1313 Far Hills Avenue (Vacant Lot): The lot at 1313 Far Hills has been advertised for sale. Details may be found at the following link: 1313 Far Hills for Sale Upcoming Work: Devereux Drive Concrete Roadway: Crews will be on site tomorrow morning, Friday, June 28, to begin pouring the concrete roadway. Pouring the … Continued

Far Hills Storm Sewer Reconstruction Project Update – 5/21

Project Highlights: Storm Sewer Work on Forrer Boulevard: Kinnison has successfully installed the storm sewer system from Far Hills to E. Schantz. Despite several heavy rainfall events in recent months, the new system has performed exceptionally well, preventing sustained ponding in previously problematic areas throughout the project corridor. 1313 Far Hills Avenue (Vacant Lot): As … Continued

Far Hills Storm Sewer Reconstruction Project Update – 5/3

Project Highlights: Storm Sewer Construction on Forrer Boulevard (Phase 3): Kinnison Excavating crews have completed the majority of storm sewer construction along Forrer Boulevard, from Far Hills to E. Schantz. We anticipate that construction of the sewer main will be completed by the week of May 13, weather permitting. Upcoming Work:  Reconstruction of Devereux Drive: … Continued

Far Hills Storm Sewer Reconstruction Project Update – 3/7

Project Highlights: Storm Sewer Construction on Devereux Drive: Kinnison Excavating crews have completed the majority of storm sewer construction along Devereux Drive. This includes the main trunk line and most “branches” leading to storm sewer inlets along the road. Backfilling with gravel was completed last month. Devereux Drive remains closed to through traffic as we … Continued

Far Hills Storm Sewer Reconstruction Project Update – 12/22

Project Highlights: Kinnison Excavating has substantially completed and restored Phase 1: The phase, covering Dellwood Avenue and northbound Far Hills Avenue, is substantially complete and open to traffic and parking per the posted restrictions. Progress on Phase 2 (Devereux Drive):  Excavation, pipe laying, and temporary restoration has been completed on about 2/3 of the new … Continued

Far Hills Storm Sewer Reconstruction Project Update – 11/30

Schedule Change for Upcoming Work: It was last reported that the curb on the north side of Dellwood would occur this week, week of 11/27. Due to sustained freezing temperatures, the subcontractor (Oglesby) is now tentatively scheduled to replace the curb early in the week during the week of 12/3. Kinnison Excavating will begin demolition … Continued

Far Hills Storm Sewer Reconstruction Project Update – 11/17

Project Highlights: Kinnison Excavating and subcontractors have substantially completed restoring the areas within Phase 1 of the Far Hills Storm Sewer Replacement project, which covers northbound Far Hills Ave., Dellwood Ave. and extends across E. Schantz Ave. Dellwood Avenue Concrete Roadway Restoration:  Kinnison is finished with all roadway restoration along Dellwood, save some minor patches … Continued

Far Hills Storm Sewer Reconstruction Project Update – 11/3

Project Highlights: Kinnison Excavating and subcontractors have made progress in restoring the areas within Phase 1 of the Far Hills Storm Sewer Replacement project, which covers northbound Far Hills Ave., Dellwood Ave. and extends across E. Schantz Ave. Liapis Landscaping resodded ~2,000 square feet within an easement between a couple of lots on Dellwood affected … Continued

Far Hills Storm Sewer Reconstruction Project Update – 10/24

The top priority is roadway, curb and associated site restoration along Dellwood between Far Hills and E. Schantz, and along the east side of Far Hills heading south from Dellwood.  City staff has applied heavy pressure on the contractor (and concrete sub-contractor) to complete this work as soon as possible.  The restoration schedule is as … Continued

Far Hills Storm Sewer Reconstruction Project Update – 10/6

Project Highlights: Kinnison Excavating has made significant progress in Phase 1 of the Far Hills Storm Sewer Replacement project, which covers Dellwood Ave. and extends across E. Schantz Ave. Despite some delays due to gas and water main conflicts and inclement weather, the storm sewer installation is now nearly complete in this phase. The team … Continued